Click to visit our web site
Click here to get closer!

KFMC -
News
Markets
Weather
Sports
Contests
About KSUM
About KFMC
Advertising
Email Us


Click here to get started.

EEO Information
Classic KFMC on Facebook
KSUM Country on Facebook
Minnesota Gas Prices
Minnesota Road Construction Info
Iowa Road Construction Info
Fairmont Public Schools
Granada-Huntley-East Chain Schools
Martin County West Schools
Martin Luther High School
Truman Public Schools
City of Fairmont
Martin County Government
Jackpot Junction
Blizzard Snowmobile Club
Martin County Humane Society
March of Dimes WalkAmerica
MS Walk
THIS PAGE SPONSORED BY PETERSON ANTHONY INSURANCE

News


07/05/2012

MARTIN COUNTY HIGHWAY ENGINEER KEVIN PEYMANN PROVIDED AN UPDATE ON THE PROGRESS OF THE COUNTY ROAD 39 (FAIRGROUNDS ROAD) PROJECT TO MARTIN COUNTY COMMISSIONERS. HE SAYS THERE HAS BEEN SOME DELAY CAUSED BY THE EXTREME HEAT THE PAST WEEK OR SO BUT CONCRETE PAVING ON THE SECTION OF THE HIGH WAY FROM COUNTY ROAD 130 TO I-90 IS PROGRESSING AHEAD OF SCHEDULE AND SHOULD BE COMPLETE IN THE NEXT COUPLE OF WEEKS. THE MN DOT WORK ON THE EXIT AND ENTRANCE RAMPS ON 1-90 SHOULD BE DONE AS WELL AND COUNTY ROAD 39 SHOULD BE OPEN BY THE FIRST WEEK IN AUGUST. TH E WORK ON THE SOUTH END OF THE PROJECT-RAILROAD TRACKS TO COUNTY ROAD 26 (OLD 16)- WILL NOT BEGIN UNTIL AFTER THE MARTIN COUNTY FAIR HAS RUN ITS COURSE.

MR. PEYMANN SAID THE RECONSTRUCTION WORK ON 100TH STREET(THE FAIRMONT TREE DUMP ROAD) HAS NOT BEEN SCHEDULED BUT SHOULD COME SOON AFTER THE COUNTY HIGHWAY DEPARTMENT COMPLETES THEIR SEALCOAT WORK. MARTIN COUNTY ,ROLLING GREEN TOWNSHIP AND THE CITY OF FAIRMONT ARE COOPERATING ON THAT PROJECT.


ROD HALVORSEN
© 2010 KSUM.


Back


Click Here To Advertise!
Click Here To Advertise!

| HOME PAGE | NEWS | MARKETS | EMPLOYMENT | WEATHER |
| SPORTS | CONTESTS | ABOUT KSUM | ABOUT KFMC |
| ADVERTISING | EMAIL US | HIDDEN PAGES |


© 2013 KFMC 106, KSUM 1370 -- All Rights Reserved.

Lawrence and Schiller: Putting the Web to Work